Two 95 MVA 426kV transformers have been positively tested

Last week we have positively performed the FAT of two 95MVA transformers with a 426/14 kV ratio for an important Norwegian hydropower plant.

The transformers, which in the final installation will be equipped with oil / SF6 insulators, were tested with temporary oil / air insulators and the heating test was carried out by connecting them to the water circuit available at TIRONI for the OFWF transformer’s tests.

The FAT was performed both in presence, with a Customer’s consultant here in Modena, and remotely, with the Customer connected to our UHV Test Lab trough the TIRONI REMOTE FAT system.

The first unit has already left the Modena factory and it’s along the road that will take it to Norway where Elettromeccanica Tironi is also in charge of removing, disposing and replacing all the 420kV SF6 busbar and the old units.

A large turnkey project!

   